Early Works Package 2 commences on the $740 million Liverpool Health and Academic Precinct (LHAP)

Early works to prepare the site for construction commenced in January 2020 and will continue into 2021 across two packages of works - Early Works Package 1 and Early Works Package 2. 

Package 2 of early works is being delivered by contractor, Multiplex. The works in this package includes:

  • construction of a temporary education facility on Eastern Campus
  • reconfiguration and connection of P1 and P3 car parks
  • temporary relocation of engineering office, distribution centre and telephone switch room
  • new kitchen facility
  • new mortuary
  • refurbishment works.
These work zones are detailed in the map below.

The impacts to our hospital visitors include:
  • reduced parking in P1, P2 and P3 car parks (accessible parking spaces will be maintained where possible)
  • alternate pedestrian routes around the hospital
  • potential dust, noise and vibration during demolition.

The safety of our patients and visitors is a priority at all times. We encourage everybody to follow signs and traffic control that will be in place to ensure safe travel around the construction site. Should you have any questions, please contact the LHAP team on (02) 8738 6670 or email SWSLHD-LHAP@health.nsw.gov.au

We thank you for your assistance and appreciate your patience as we build the Liverpool Health and Academic Precinct.
 
LOCATION OF EARLY WORKS (PACKAGE 2) ON THE HOSPITAL CAMPUSed/altered vehicle and pedestrian access

Reduet ping

Dust, noise and vibration

Restricted access to the campus traffic bridge.

Please follow signage and directions for your safety, and allow extra time in case of delays.